The Uusi-Summa sports hall project is progressing as planned – the project will be completed in October
The construction of the Uusi-Summa sports hall in the city of Hamina is progressing well. The hall and its courtyard areas will be completed by the end of October.
The construction of the sports hall has progressed smoothly since the City of Hamina took over as the main contractor. There have been no new surprises in the project, and appropriate quality assurance has been carried out during the project.

The original completion schedule for the project was early September 2026, so there will be a few months of delay to the original plan. The sports hall, including yard work, will be handed over for use by the end of October. The yard design has taken into account the number of users in the area, and the site will have ample parking space.
Although the original project schedule was hit and miss, we have managed to get the situation under control as the city's own project. There is now a strong sense of activity on the site,
says Hamina's urban development manager, Toni Puustinen.The total budget for the construction project is about to exceed the original plan by approximately 400,000 euros.